PERT and critical path
A PERT chart shows activities and dependencies as a network rather than as bars, which makes the critical path visible: the sequence with no slack, where any delay is a delay to the whole project.
It is the diagram to draw when someone asks what would actually happen if a task slipped.
#When to reach for one
Schedule risk analysis before committing to a date.
Explaining why one task matters more than three others.
Comparing plans, where the critical path differs between options.
#How to draw it in Capable
Route | Use when |
|---|---|
Graphviz | Networks with automatic layout, which suits activity graphs. |
draw.io | Annotated versions with durations and slack marked. |
#A worked example
Activities, durations, and a critical path in bold:
The source, which you can paste into a new diagram and edit:
#A few things that catch people out
Slack is the useful number. Tasks with slack can absorb delay; tasks without cannot.
The critical path moves when estimates change. Recalculate rather than trusting last month's diagram.
Three-point estimates (optimistic, likely, pessimistic) are the original point of PERT and still useful.